In 2008, Western Power submitted an application for the ERA to determine that forecast new facilities investment proposed by Western Power for a 330 kV transmission line and associated works in the Mid-West region of Western Australia meets the new facilities investment test.

In 2008 the ERA pre-approved an amount of $300 million for Western Power to construct a 330 kV transmission line and associated works in the Mid-West region of Western Australia.

Papers

Date Documents File type
04-Sep-08 Final Determination
Adobe PDF 143 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
04-Aug-08 Draft Determination
Adobe PDF 139 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
23-May-08 Issues Paper
Adobe PDF 228 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT

Western Power's application

Date Documents File type
23-May-08 NFIT Application - Western Power - Covering Letter to the Authority
Adobe PDF 372 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
23-May-08 NFIT Application - Western Power - Submission (Public Version)
Adobe PDF 216 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT

Public submissions received in response to draft decision

Date Documents File type
19-Aug-08 Public Submission - Alinta Sales - Draft Determination
Adobe PDF 935 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT

Public submissions received in response to issues paper

Date Documents File type
13-Jun-08 Public Submission - Mid West Development Commission
Adobe PDF 40 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
12-Jun-08 Public Submission - Western Power
Adobe PDF 68 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
11-Jun-08 Public Submission - Alinta Sales
Adobe PDF 33 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
11-Jun-08 Public Submission - Extension Hill
Adobe PDF 488 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
11-Jun-08 Public Submission - Geraldton Iron Ore Alliance
Adobe PDF 62 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
11-Jun-08 Public Submission - Griffin Energy
Adobe PDF 955 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
11-Jun-08 Public Submission - Office of Energy
Adobe PDF 797 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
09-Jun-08 Public Submission - Aviva Corporation
Adobe PDF 25 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>330kV Mid-West Augmentation - NFIT
Page last updated: 13 Oct 2020