Skip to content

66/11 kV Medical Centre Zone Substation expansion and voltage conversion of distribution network

In 2008 the ERA determined that an amount of $24.9 million may satisfy the new facilities investment test for Western Power to construct a 66/11 kV zone substation and associated distribution works at Sir Charles Gairdner Hospital.

Papers

Date Documents File type
19-Feb-09 Final Determination on the New Facilities Investment Test for a 66/11 kV Medical Centre Zone Substation Expansion and Voltage Conversion of the Distribution Network
Adobe PDF 190 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
19-Feb-09 Geoff Brown & Associates Ltd - New Facilities Investment Test - Medical Centre Substation
Adobe PDF 483 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
11-Dec-08 Draft Determination on the New Facilities Investment Test for a 66/11 kV Medical Centre Zone - Substation Expansion and Voltage Conversion of the Distribution Network
Adobe PDF 147 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
11-Dec-08 New Facilities Investment Test For Western Power’s Medical Centre Zone Substation - Technical Review
Adobe PDF 98 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
26-Sep-08 Issues Paper - New Facilities Investment Test for a 6611 kV Medical Centre Zone Substation Expansion
Adobe PDF 211 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT

Western Power's application

Date Documents File type
26-Sep-08 Major Augmentation Proposal - Western Power - Covering Letter to the Authority
Adobe PDF 336 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
26-Sep-08 Major Augmentation Proposal - Western Power - Submission
Adobe PDF 114 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT

Public submissions received in response to draft decision

Date Documents File type
08-Jan-09 Public Submission - Draft Decision - Alinta Sales Pty Ltd
Adobe PDF 225 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
08-Jan-09 Public Submission - Draft Decision - Department of Health, North Metro Area Health Service
Adobe PDF 1 MB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
08-Jan-09 Public Submission - Draft Decision - Western Power
Adobe PDF 92 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT

Public submissions received in response to issues paper

Date Documents File type
22-Oct-08 Public Submission - Western Power
Adobe PDF 106 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
14-Oct-08 Public Submission - Alinta Sales Pty Ltd
Adobe PDF 808 kB

Description: (Electricity Access Division) Third Party Access>Electricity>Network Augmentations>66/11kV Medical Centre Zone Substation Augmentation - NFIT
Page last updated: 13 Oct 2020