The ERA approved an application from Western Power to be temporarily exempted from complying with the requirements of clause 2.5.4(b) (Normal Cyclic Rating Criterion) of the Transmission Planning Criteria in the Technical Rules at Meadow Springs zone substation until the completion of Stage 2 of the Mandurah load area investment strategy, or unless otherwise revoked under the provisions of the Electricity Networks Access Code 2004.

Western Power submitted an application to the ERA for an exemption from the Technical Rules in May 2015. As part of the consultation and review process, the ERA published an issues paper and invited interested parties to make submissions on Western Power’s application. One submission was received from Community Electricity.

The ERA engaged Geoff Brown and Associates as technical advisors to provide a report on Western Power’s exemption application.

The ERA received an application made under section 12.45 of the Access Code from Mr Stephen Davidson to revoke the exemption in December 2016. 

On 14 February 2019, a consultation paper on Mr Stephen Davidson’s application was published with interested parties invited to make submissions. The consultation paper and submissions are published here.

Papers

Date Documents File type
20-Jul-15 Determination on Application for exemption from certain requirements of the Technical Rules submitted by Western Power
Adobe PDF 91 kB

Description: Determination on application for exemption from certain requirements of the technical rules submitted by western power ic cxempt ERA
20-Jul-15 Review of western power’s application for a technical rules exemption for meadow springs zone substation
Adobe PDF 725 kB

Description: Review of western power s application for a technical rules exemption for meadow springs zone substation ic cxempt ERA
18-Jun-15 Issues paper on WP Application for exemption from Technical Rules for Meadow Springs Zone Substation
Adobe PDF 285 kB

Description: Issues paper on WP Application for exemption from Technical Rules for Meadow Springs Zone Substation
18-Jun-15 Western Power application for tech rules exemption - Meadow Springs Zone Substation
Adobe PDF 31 MB

Description: Western power application for tech rules exemption meadow springs zone substation ic cetw ERA

Public Submissions

Date Documents File type
20-Jul-15 Community Electricity - Meadow Springs Substation exemptions public submission
Adobe PDF 63 kB

Description: Community electricity meadow springs substation exemptions public submission ic cxempt ERA