Proposed amendments submitted in April 2016

In April 2016, Western Power proposed the following amendments to its Technical Rules:

  • amendments to the wording of the Normal Cyclic Rating (NCR) criterion,which outlines the permissible level of power loss following the unplanned loss of a supply transformer at a substation
  • the replacement of references to Electricity (Supply Standards and System Safety) Regulations 2001 with references to Electricity (Network Safety) Regulations 2015
  • correction of an incorrect cross reference in Clause 4.2.1(b)
  • correction of the misspelling of the word “Distribution” in the title of Section 5
  • additions to the Glossary of the Technical Rules that will allow the Rules to automatically adopt revisions to Standards and Regulations “as amended from time to time”.

The ERA published its final decision in November 2016. 

The revised Technical Rules took effect on 1 December 2016.

Papers

Date Documents File type
09-Nov-16 Final Decision on Western Power’s Proposed Amendments to the Technical Rules (Submitted April 2016)
Adobe PDF 481 kB

Description: Final Decision on Western Power’s Proposed Amendments to the Technical Rules (Submitted April 2016)
09-Nov-16 Technical Consultants Report on Western Power’s Proposed Amendments to the Technical Rules
Adobe PDF 275 kB

Description: Technical Consultants Report on Western Power’s Proposed Amendments to the Technical Rules
07-Sep-16 Draft Decision - WP Tech Rule Amendments April 2016
Adobe PDF 347 kB

Description: Draft Decision - WP Tech Rule Amendments April 2016
07-Sep-16 GBA report March and April 2016
Adobe PDF 516 kB

Description: GBA report March and April 2016
02-May-16 Issues Paper -Tech Rules amendments Submitted April 2016
Adobe PDF 373 kB

Description: Issues Paper -Tech Rules amendments Submitted April 2016
02-May-16 WP Tech Rule Amendments April 2016
Adobe PDF 191 kB

Description: Western Power Tech Rule Amendments April 2016

Public Submissions

Date Documents File type
04-Oct-16 Public Submission – Draft Decision– Steve Davidson
Adobe PDF 533 kB

Description: Public Submission – Draft Decision– Steve Davidson
04-Oct-16 Public Submission – Draft Decision– Western Power
Adobe PDF 2 MB

Description: Public Submission – Draft Decision– Western Power
08-Jun-16 Public Submission (Late) - Issues Paper - James Davidson April 2016 Normal Cyclic Rating Clause 2 5 4 (002)
Adobe PDF 389 kB

Description: Public Submission (Late) - Issues Paper - James Davidson April 2016 Normal Cyclic Rating Clause 2 5 4 (002)
Page last updated: 18 Jan 2024